Realization progress

31. 12. 2020
Completion of 81 km of the gas pipeline

19. 2. 2020
Completion of tree planting in compensation for the non-forest tree felling for the whole project

31. 12. 2019
Completion of 20 km of the pipeline and the technology building of Výrava border point station

11. 12. 2019
Completion of the delivery of piping material for the straight-line section

20. 06. 2019
Commencement of welding works

18. 09. 2018
Project kick-off ceremony

29. 06. 2018
Granting of the building permit

20 .12. 2017
Signing of a grant agreement by INEA, GAZ-SYSTEM and EUSTREAM for the construction of the Poland - Slovakia Gas Interconnector

23. 11. 2017
Inclusion of the project in the third list of the European Union’s Projects of Common Interest (PCI)

21. 08. 2017
Granting of the land-use decision authorising the situation of the Poland - Slovakia Gas Interconnector construction project and issuance of the relevant public notice by the District Authority of Prešov

17. 02. 2017
Positive assessment of the Poland - Slovakia Gas Interconnector project by the European Commission for CEF financial support for the project implementation in the total amount of € 107.7 million, of which € 55.232 million is earmarked for the Slovak part of the project

08. 12. 2016
Lodging of EUSTREAM’s application for the construction project situation decision

08. 11. 2016
Lodging of a joint application for a Connecting Europe Facility (CEF) grant for project works by EUSTREAM and Gaz-System

26. 08.  2016
Announcement of the Open Season procedure for the Poland - Slovakia Gas Interconnector by EUSTREAM and Gaz-System

11. 08. 2016
Issuance of the Certificate for Construction of Energy Facility by the Ministry of Economy of the Slovak Republic for the construction of the Poland - Slovakia Gas Interconnector in the territory of the Slovak Republic

18. 02. 2016
Issuance of the Certificate for Construction of Energy Facility by the Ministry of Economy of the Slovak Republic for the modification of the Compressor Station 01 Veľké Kapušany under the Poland - Slovakia Gas Interconnector project

21. 01. 2016
Issuance of the Final Environmental Impact Assessment (EIA) Opinion by the Ministry of Environment of the Slovak Republic

18. 11. 2015
Inclusion of the project in the second list of the European Union’s Projects of Common Interest (PCI)

18. 05. 2015
Signing of a grant agreement by INEA (Innovation and Networks Executive Agency), EUSTREAM and Gaz-System for CEF financial support for the “Preparatory Studies and Engineering Works for the Poland – Slovakia Gas Interconnector” action

22. 11. 2013
Signing of the Cooperation Agreement between the Government of the Slovak Republic and the Government of the Republic of Poland for cooperation in the implementation of the Poland – Slovakia Gas Interconnector project

14. 10. 2013
Inclusion of the project in the first list of the European Union’s Projects of Common Interest (PCI)

30. 04. 2013
Delivery of a feasibility study for the Poland – Slovakia Gas Interconnector project by GAZOPROJEKT S.A

29. 03. 2012
Signing of the Feasibility Study Agreement for the Poland – Slovakia Gas Interconnector project