SPP EUSTREAM image
 

312/2014 REQUIREMENTS

 
 
Pursuant to Commission Regulation (EU) No. 312/2014 of 26 March 2014 establishing a Network Code on Gas Balancing of Transmission Networks Eustream publishes following information:

Balancing Network Code Information
Article 8 (7)
Information with regard to the balancing services procured and the related costs incurred
year 2018:
Sum of all related costs:
2 026 267 EUR
Article 9 (4)
Information with regard to the costs, frequency and quantity of the balancing actions undertaken
year 2018:
Balancing actions
Article 20 (2)
Daily imbalance charge calculation methodology 
Operational Order
Price decision

Article 29 (4)
Data regarding the aggregate balancing related charges and the aggregate neutrality charges for balancing  
Neutrality account